Factory Construction Cost and Process: Turnkey Stages

Betek Balıkesir Taşyünü Fabrikası ve Ofis Binası İnşaatı – görsel 1

For a new factory investment, the first questions are usually cost and schedule. Both become far more predictable once you understand which decisions drive them. Below we outline the factory construction process and the main cost items.

In short

  • Ground, structural system, roof-cladding and process requirements drive factory cost the most.
  • Compare quotes by scope, exclusions and change management, not only by the total.
  • Early survey, clear scope and written change management reduce budget deviation.
  • Phased investment planning can lower the initial investment.

Main factors that determine cost

  • Ground conditions: Depending on the soil survey, ground improvement, piles or wide foundations may be required.
  • Built area and height: Floor area matters, but so do column spans and clear height, which shape the structural system.
  • Structural system: Reinforced concrete, steel and precast systems balance time and cost differently.
  • Process requirements: Machine loads, vibration, clean areas and utility lines change floor and roof details.
  • Location and infrastructure: Inside an organized industrial zone utilities are ready; outside, roads, power and water connections enter the budget.

Stages of turnkey factory construction

  1. Survey, soil investigation and preliminary design
  2. Excavation, ground improvement and foundations
  3. Structure, roof and cladding
  4. Industrial flooring, offices and ancillary buildings
  5. Testing, acceptance and handover

Practices that shorten the schedule

Overlapping design and construction, ordering materials early and working with a single point of responsibility keep the schedule under control. For example, the Es Global integrated production facility combines production lines, storage areas and administrative buildings in one complex.

What information is needed for a proposal?

For a sound cost study, the contractor needs:

  • Plot location, zoning status and soil survey report
  • Estimated closed area, clear height and office/social area share
  • Production or storage process and machine loads
  • Target handover date and ramp-up calendar
  • Any existing design, site plan and utility connection values

How is cost kept under control?

When scope, unit prices and change management are written into a turnkey contract up front, budget deviation falls. Three habits make the difference: defining scope in detail, approving change requests with a price during construction, and fixing material choices early.

The critical path in the schedule

The items that most affect a factory schedule are the permit process, foundation and ground works, and erection of the structure. Overlapping them (for example, starting precast production while foundations are built) shortens total time. Because weather affects excavation and concrete works, the schedule should be built around the season.

Cost items in detail

ItemImpactNote
Ground and foundationsHighImprovement, piles or wide foundations per the survey
Structural systemHighReinforced concrete, precast or steel changes time and cost
Roof and claddingMediumSystem chosen per insulation and fire needs
Industrial floorMedium-HighSpecial details may be needed for machine and vehicle loads
Utilities and site worksMediumOutside an OIZ, roads, power and water connections are added
Administrative and social buildingsLow-MediumDepends on quality level and area

How to read a turnkey quote

When comparing quotes, looking only at the total can mislead. What the scope includes, what is excluded and the unit-price basis should be examined one by one.

What to check in a quote

  • ✓Detail of scope and technical specification
  • ✓Excluded items and owner-supplied works
  • ✓Pricing method for changes (variations)
  • ✓Progress payment and payment plan
  • ✓Handover date and delay conditions
  • ✓Warranty and after-handover support

Habits that prevent budget overruns

1

Define scope in detail

Every item left vague returns as extra cost during construction.

2

Commission the soil survey early

Foundation solution is one of the biggest cost uncertainties.

3

Fix material choices early

Late decisions cause both price and schedule deviation.

4

Manage changes in writing

Changes during construction should be priced and approved before execution.

Optimizing without cutting quality

The way to lower cost is not to reduce quality but to design efficiently. Standard and modular column spans, repeated structural elements, a simple building form that follows the production flow and early orders of critical materials are the basics of a value-engineering approach. Gains are highest when this work is done at the survey stage.

Note

The topics here describe the general framework; a firm budget requires a project-specific survey and preliminary design.

Common mistakes in factory cost

  • Deciding on a square-meter unit price alone
  • Choosing roof, cladding and floor quality without comparing quotes like for like
  • Not reflecting permit time in the schedule
  • Leaving administrative building, site and landscaping works out of the budget
  • Zeroing the expansion allowance for short-term savings

Balancing schedule and cost

As time shortens, site overheads fall, but acceleration measures (extra shifts, early material orders) can add cost. The right balance depends on the commercial value of the start-up date: if a delay is costly for the business, extra investment for faster delivery often pays off.

Payment plan and progress payments

In turnkey contracts, payment is usually made through progress payments tied to works completed. Writing the measurement basis, payment periods and acceptance criteria down at the start gives transparency to both owner and contractor, and the payment plan should be assessed together with financing terms.

Frequently asked questions

Can square-meter cost be given as a single figure?
No. Two factories with the same closed area can differ widely in cost depending on ground, structure, process and location. A sound figure comes after survey and preliminary design.
Is there an ideal season to build a factory?
Excavation and concrete works can be harder in winter, but with proper planning and precautions it is possible to work all year.
Does it make sense to build a factory in phases?
If expansion is planned, yes. Setting up infrastructure and plot layout for final capacity and splitting the building into phases lowers the initial investment. For a detailed guide see our factory construction guide.
Which items belong in a factory budget?

Building, floor, utilities, site works, administrative building, design and permit costs and a contingency allowance should be considered.

Examples of factory projects of different scales that we completed:

Let’s take the first step on your project

Share your plot, scope and target handover date and we will get back to you with a survey and proposal.

Request a survey & proposalCompleted projects

info@dea.com.tr · +90 (216) 527 48 00

+90 (216) 527 48 00LinkedInYouTubeCorporate VideoE-Catalogue